Through early contractor involvement, Story was able to attend meetings with the client to advise on key areas of the works. This included carrying out a stone measure and ordering the stone ahead of time to ensure that when it was time to start on site, the team hit the ground running with a constant flow of stone deliveries.
It was agreed that Story would change subcontractor for the stonework, so as to ensure completion of the works within the allocated timescales, as the original supplier didn’t instil confidence that they would be able to finish the project in 2024.
The newly selected subcontractor not only fulfilled the original scope of works, but eventually installed more than double the amount of stone replacement than was expected at the tender stage.
Thanks to the hard work of everyone on site, all the repair works were successfully completed by the end of November 2024.