Smardale Gill Viaduct Masonry Repairs

Following the successful re-waterproofing of the Grade II listed structure in 2023, Story were contracted to carry out masonry repairs to the arches and piers of the viaduct.

148
stones repaired

1,900m2
of existing stonework repointed

20m3
of lime grout installed

The Scope

The project involved the following main work activities:

  • Protect the surrounding site of Special Scientific Interest and Special Area of Conservation.
  • Set up of temporary works
  • Replacement damaged and missing stone
  • Piecing in of existing stone
  • Installation of cintec anchors
  • Re-pointed existing stone work
  • Vegetation management
  • Lime grouting to existing voids

Delivering Success

Through early contractor involvement, Story was able to attend meetings with the client to advise on key areas of the works. This included carrying out a stone measure and ordering the stone ahead of time to ensure that when it was time to start on site, the team hit the ground running with a constant flow of stone deliveries.

It was agreed that Story would change subcontractor for the stonework, so as to ensure completion of the works within the allocated timescales, as the original supplier didn’t instil confidence that they would be able to finish the project in 2024.

The newly selected subcontractor not only fulfilled the original scope of works, but eventually installed more than double the amount of stone replacement than was expected at the tender stage.

Thanks to the hard work of everyone on site, all the repair works were successfully completed by the end of November 2024.

The Story Way

Smardale Gill Viaduct is a Grade II listed structure, situated within an area of Special Scientific Interest and Special Area of Conservation. As such works were planned to ensure no negative impact on either the structure or the surrounding environment, with ecologists attending site throughout the projects to ensure the protection of local wildlife.

The structure also forms part of a popular walking route and as such, all works were planned in order to allow public access to be maintained throughout.

Related projects

View all
Hope Valley Railway Upgrade
Infrastructure

Hope Valley Railway Upgrade

Network Rail

Infrastructure
View project

VolkerRail/Story joint venture were tasked with the £80m project as part of a £137m investment that saw the undertaking of extensive enhancement works to remove several bottlenecks along the route to improve reliability, increase passenger services and aid in freight movements.

View project
Burton Underpass
Infrastructure

Burton Underpass

Ayrshire Roads Alliance

Infrastructure
View project

Essential works took place to replace the unsafe road crossing over Dunure Road by reopening a former railway tunnel as a new underpass.

View project
Royal Border Bridge
Infrastructure

Royal Border Bridge

Network Rail

Infrastructure
View project

Upon inspection it was identified that the structure was suffering from defects such as loose brickwork, open joints, parapet leaning/bulging, fractured pattress plates and other minor works areas typical of masonry.

View project

To find out how we can help deliver your future project then get in touch