Hope Valley Railway Upgrade

VolkerRail/Story joint venture were tasked with the £80m project as part of a £137m investment that saw the undertaking of extensive enhancement works to remove several bottlenecks along the route to improve reliability, increase passenger services and aid in freight movements.

24 blockades
to facilitate delivery

£63.7m
social value created in community

The Scope

The scope of the project is to design and implement the following works:

  • Construction of a new platform and AFA footbridge at Dore & Totley station, along with the extension of the original platform.
  • Installation of new track in Dore, including the construction of a contig piled retaining wall.
  • Construction of a new railway loop between Bamford and Hathersage, including soil nailing & regrade work.
  • Construction of a new overbridge at Hathersage West, replacing the current foot crossing to improve safety.
  • Signalling improvements along the line to improve reliability, including removing the redundant signal boxes in Totley and Grindleford.

Delivering Success

The project has been able to celebrate success and demonstrate best practice within the following areas:

  • The project was enabled by a Transport and Works Act Order which demanded, through planning conditions, a high standard of environment sustainability through implementing the project. This included developing a range of Code of Construction Management Plans, covering how environmental and social risks would be reduced and positive impacts realised.
  • The team have responded to challenges on site with innovative solutions. This includes transporting Hathersage footbridge 1.5km down the track to its final
    location using LEMS, which are usually only used for track installation, to allow the structure to fit under a stone road bridge which had limited clearance. The team also carried out a tandem lift of structure TJC1/36 using two kirow 1200 machines in bespoke configuration involving a salmon trailer, due to the weight of the structure and the team being unable to use any other form of heavy lift equipment close to the site of install.
  • The team have demonstrated good reactive working in response to opportunities made available to the project through industrial action windows which maximised track access.

The Story Way

To maintain positive relationships with local residents & lineside neighbours while delivering the project, quarterly community engagement events are run and innovative stakeholder & communication tools have been implemented, such as a digital noticeboard and project app. The project team also committed to each member of staff carrying out a minimum of two days’ volunteering in the local community. This has resulted in 2478 volunteering hours being delivered and 3286 students engaged with (as of October 2023) This included during Storm Babet, when the project team assisted local businesses impacted by flooding, through using buckets and moving ballast bags to help remove and stop the flow of the rising water.

Related projects

View all
Seaton South Embankment Upgrade
Rail

Seaton South Embankment Upgrade

Network Rail

Rail
View project

The project involved regrading approximately 280 metres of the embankment to enhance structural stability and improve rail safety.

View project
SPT Broomloan Depot
Rail

SPT Broomloan Depot

SPT

Rail
View project

Story Contracting Ltd were engaged by Ansaldo STS (Hitachi) as their principal contractor to support the comprehensive upgrade of the Glasgow Subway network for SPT (Strathclyde Partnership for Transport).

View project
Shields Road
Rail

Shields Road

Network Rail

Rail
View project

Story Contracting replaced a key bridge linking Pollokshields and Kinning Park, maintaining pedestrian access via a temporary footbridge while managing complex utility diversions, major excavations, and two disruptive possessions.

View project

To find out how we can help deliver your future project then get in touch

"*" indicates required fields