Seaton South Embankment Upgrade

The project involved regrading approximately 280 metres of the embankment to enhance structural stability and improve rail safety.

22,000t
of 6F5 used for regrade works

280m
regrade complete

The Scope

The scope of the project was to design and implement the following works:

  • Excavate and step the existing embankment face in 10m sections.
  • Installation of Terram to the excavated sections.
  • Installation of stone to the embankment face, decreasing the slope angle.
  • Installation of safe cess walkway.
  • Installation of drainage to the toe of the embankment.
  • Install new access track, install new fence lines and reinstate the landowners land.

Delivering Success

The project successfully demonstrated best practice across several key areas:

The scheme presented several challenges, including strict landowner agreements and a compressed delivery timeframe. In addition to regrading the embankment, the scope was expanded to include the construction of a new access track for the landowner and the installation of new fencing along the affected area.

Success was achieved through early engagement with the landowner, which helped foster positive community relations. The team also sourced stone strategically from local quarries, securing competitive rates that exceeded expectations. Furthermore, proactive management of unforeseen changes ensured the project was completed on time despite additional works being introduced.

The Story Way

Collaboration was the cornerstone of this project, driving its success from start to finish. From the outset, the team established a strong partnership with both the designer and the landowner, ensuring that every stage of the scheme was underpinned by open and transparent communication. Regular updates, clear explanations of the works, and a willingness to listen to feedback created a positive and cooperative environment.

This proactive approach meant that any concerns were identified early and resolved quickly, preventing potential delays and maintaining momentum throughout the delivery phase. By fostering trust and building strong relationships, the team not only met the technical requirements of the project but also strengthened community confidence in the work being carried out.

Related projects

View all
Hope Valley Railway Upgrade
Rail

Hope Valley Railway Upgrade

Network Rail

Rail
View project

VolkerRail/Story joint venture were tasked with the £80m project as part of a £137m investment that saw the undertaking of extensive enhancement works to remove several bottlenecks along the route to improve reliability, increase passenger services and aid in freight movements.

View project
SPT Broomloan Depot
Rail

SPT Broomloan Depot

SPT

Rail
View project

Story Contracting Ltd were engaged by Ansaldo STS (Hitachi) as their principal contractor to support the comprehensive upgrade of the Glasgow Subway network for SPT (Strathclyde Partnership for Transport).

View project
Shields Road
Rail

Shields Road

Network Rail

Rail
View project

Story Contracting replaced a key bridge linking Pollokshields and Kinning Park, maintaining pedestrian access via a temporary footbridge while managing complex utility diversions, major excavations, and two disruptive possessions.

View project

To find out how we can help deliver your future project then get in touch

"*" indicates required fields