Seaton South Embankment Upgrade
Network Rail
The project involved regrading approximately 280 metres of the embankment to enhance structural stability and improve rail safety.
3No 54 Hour
possessions utilised
500T & 450T Cranes
used to lift structures
The scope of the project was to design and implement the following works:
Prior to any works commencing on Muirhead Road overbridge we issued letters to all the residents in the surrounding area, detailing the works which would be carried out and the importance of these works to improve the existing road over the railway.
This helped reduce the impact of our presence as the locals were aware of why we were there and how long for- an important factor as the road had to be closed permanently for a period of time and a diversion put in place.
We were able to celebrate success in the project through:
This project has not been without its challenges and the team at Story have addressed a problem which has been of concern to Network Rail for some time. Thanks for your hard work which has delivered a great result for not only Network Rail, but also the Local Authority, pedestrians, road and rail users alike.
Network Rail
The project involved regrading approximately 280 metres of the embankment to enhance structural stability and improve rail safety.
RWE Renewables
Works were carried out to demolish an existing storage building, and replace it with a larger, modern structure.
Network Rail
VolkerRail/Story joint venture were tasked with the £80m project as part of a £137m investment that saw the undertaking of extensive enhancement works to remove several bottlenecks along the route to improve reliability, increase passenger services and aid in freight movements.