Seaton South Embankment Upgrade
Network Rail
The project involved regrading approximately 280 metres of the embankment to enhance structural stability and improve rail safety.
16,000
man hours worked
72
engineering trains
The scope of the project was to design and implement the following works:
Edinburgh Waverley is at the heart of the capital and a vital part of our rail network – carrying passengers across the length of Scotland and south to London on the East Coast Main Line.
“The work we have delivered over the last two years will help to make sure the station can continue to play an important role in the economic and social life of the city.
Network Rail
The project involved regrading approximately 280 metres of the embankment to enhance structural stability and improve rail safety.
Network Rail
VolkerRail/Story joint venture were tasked with the £80m project as part of a £137m investment that saw the undertaking of extensive enhancement works to remove several bottlenecks along the route to improve reliability, increase passenger services and aid in freight movements.