Ravenscraig WCML

Working alongside Network Rail and North Lanarkshire Council to install the award-winning new underbridge under the West Coast Main Line.

5000t
concrete structure

36,000t
material excavated for the new structure

£10m
Of social value delivered

The Scope

The project involved the following main phases:

• De-vegetation of all work areas
• Create access road from enterprise way to compound area
• Create compound area & set up compound
• Create access road to laydown area & casting yard
• Create laydown area & casting yard
• Install drainage to access road & casting yard
• Install dewatering system for casting yard
• Staged casting of new bridge structure
• Partial demolition and full infill of adjacent UB 031/014
• Track side temporary works
• Disruptive works including:
• Diversion of existing S&T, raising of the OLE & removal of P-Way
• Bulk earthworks
• New structure installation
• Partial demolition and full infill of adjacent UB 031/014
• Reinstatement of S&T, OLE & P-Way

Delivering Success

To help us deliver this monumental scheme, we heavily relied on our specialist supply chain partners from an early stage at tender. There are many to mention, but our main specialist supply chain partner would be Sarens, who were responsible to transporting the 5000T structure into position using Self Propelled Modular Transporters.

The Story Way

Throughout the duration of the project, the team have delivered a number of meaningful social value initiatives within the local area as part of our Community Benefits commitments with North Lanarkshire Council. This has included working closely with Developing the Young Workforce to deliver industry taster days and over 400-hours of work experience on the live construction site, created a bespoke training programme and delivered 100 hours of work experience.

Related projects

View all
Hope Valley Railway Upgrade
Infrastructure

Hope Valley Railway Upgrade

Network Rail

Infrastructure
View project

VolkerRail/Story joint venture were tasked with the £80m project as part of a £137m investment that saw the undertaking of extensive enhancement works to remove several bottlenecks along the route to improve reliability, increase passenger services and aid in freight movements.

View project
Burton Underpass
Infrastructure

Burton Underpass

Ayrshire Roads Alliance

Infrastructure
View project

Essential works took place to replace the unsafe road crossing over Dunure Road by reopening a former railway tunnel as a new underpass.

View project
Royal Border Bridge
Infrastructure

Royal Border Bridge

Network Rail

Infrastructure
View project

Upon inspection it was identified that the structure was suffering from defects such as loose brickwork, open joints, parapet leaning/bulging, fractured pattress plates and other minor works areas typical of masonry.

View project

To find out how we can help deliver your future project then get in touch