Bombo Burn Scour Protection Works

The bridge at Bombo Burn required extensive remediation in the form of scour protection works, as well as vegetation management and masonry repair works.

THE PROJECT

Structure UB162/002 located on the AYR4 023m 0880yds servicing the Bombo Burn, required extensive remediation in the form of scour protection works to lower the EX2052 risk scour score to 10 in addition to vegetation management and masonry repair works.

Story Scotland were commissioned by Network Rail to carry out the £500k worth of works. This included the installation and removal of a temporary damning system, the excavation and profiling of the riverbed and the installation of reinforced concrete invert and Rip Rap.

Through the maximisation of planned labour, plant and equipment during periods of excellent weather, the team were successfully able to mitigate any weather delays. Moreover, the early engagement with all specialist sub-contractors who worked collaboratively throughout the project enabled a smooth transition from task to task on the programme’s critical path.

Circa 200t 

Rip Rap installed

Circa 90 m3 

concrete poured

SCOPE OF ENGINEERING WORKS

The scope of the works involved:

  • Site Mobilisation & Establishment Works
  • Installation of & Removal of Temporary Damming System
  • Excavation & Profiling of Riverbed
  • Installation of Reinforced Concrete Invert
  • Installation of Rip Rap
  • De-vegetation of Structure & Masonry repairs
  • Demobilisation & Reinstatement Works

DELIVERING A SUCCESSFUL SOLUTION

The project was able to celebrate success
and demonstrated best practice within the
following areas:

  • Completion of works within programme, budget
    and with no accidents or incidents within a
    logistically challenging location.
  • The use of an effective over pumping damming
    solution to maximise productivity whilst
    maintaining a robust method of safe working
    around the structure with no disruption to rail
    traffic.
  • The revision of design levels to mitigate any risk
    which may be present of implementing works given
    the shallow foundations present supporting the
    structure.
  • The creation of a complete dry working area for an
    effective and prolonged period to allow concrete
    works to take place.
  • The success of delivering the project whilst adapting
    to working within the Covid 19 pandemic.
  • The safe and efficient delivery of the whole works
    package during challenging weather and water level
    conditions.

 

THE STORY WAY

Our project team worked in close collaboration with NWR,
environmental agencies and designers to ensure various
specialist works could be completed within the allocated time
frame for working within the watercourse, with solutions
such as an effective temporary damming system & ensuring
the works did not jeopardise the shallow foundations present
supporting the structure.

Our project team also effectively planned works and used an
innovative technology to enable the works to be planned and
implemented successfully in ever changing weather and water
level conditions

I would like to express my thanks and congratulations to everyone involved in this project. The client organisation is delighted with the successful delivery and very happy with the final product. We recognise that the timescales and the severe weather were extremely difficult to contend with and it is commendable that the scope has been achieved to such a high level of quality despite the significant challenges. I don’t need to re-emphasise the importance of scour protection schemes to the ongoing management of railway assets so I will simply say well done and excellent work.

Michael McArthur Project Manager, Capital Delivery, Scotland's Railway

Related projects

View all
Seaton South Embankment Upgrade
Rail

Seaton South Embankment Upgrade

Network Rail

Rail
View project

The project involved regrading approximately 280 metres of the embankment to enhance structural stability and improve rail safety.

View project
RWE Wind Farm
Energy

RWE Wind Farm

RWE Renewables

Energy
View project

Works were carried out to demolish an existing storage building, and replace it with a larger, modern structure.

View project
Hope Valley Railway Upgrade
Infrastructure

Hope Valley Railway Upgrade

Network Rail

Infrastructure
View project

VolkerRail/Story joint venture were tasked with the £80m project as part of a £137m investment that saw the undertaking of extensive enhancement works to remove several bottlenecks along the route to improve reliability, increase passenger services and aid in freight movements.

View project

To find out how we can help deliver your future project then get in touch