Tongland Dam Plunge Pool Repair Works

Investigation and repair works to plunge pool area at Drax’s hydro-electricity generation plant in Dumfries and Galloway.

THE PROJECT

The Plunge Pool is located downstream of the floodgates and dam spillway and forms part of the Tongland dam structure. The walls are constructed from a combination of both concrete blocks and reinforced concrete.

The walls are founded on bedrock with base of the plunge pool being rock. A concrete weir is located at the downstream end of the plunge pool where water re-joins the River Dee.

The objective of the Works is to investigate and repair the voiding behind the plunge pool walls and carry out the associated repair works to the plunge pool, spillways (walls and concrete floor slab), spillway channels and flood gate piers.

131

defects repairs completed per defects schedule

5,460

manhours achieved without any lost time injury (zero LTI)

holding volume of 6.8million litres

complete de-watering of plunge pool

DELIVERING A SUCCESSFUL SOLUTION

Early consultation with neighbours and local landowners resulted in good community relations. Project team support neighbours in carrying out repair works to their car parks driveway and garden.

Coming up with a viable option that will accelerate the works, eliminate any environmental impact to the watercourse and reduce the number of personnel exposures by the application of spray concrete (shotcrete) on deep voiding identified on the plunge pool East and West walls.

 

Project team developing a scope definition strategy and timely completion optimisation plan led to project staying on programme and within budget.

Management of unforeseen changes was proactive, resulting in additional works not affecting original completion date. Construction works progressing at work site during detailed Engineering design period.

Implementing project improvement initiatives by extending work hours, starting weekend works (Saturday and Sunday).

SCOPE OF ENGINEERING WORKS

The project to repair works to plunge pool area at Drax’s hydro-electricity generation plant involved:

  • Site Establishment and Set-Up
  • Installation of rope access system
  • De-vegetation and cleaning works on plunge pool and spillway walls
  • Design and installation of pumping system to de-water the plunge pool
  • Fish rescue of the plunge pool
  • Conduct Investigation of the extent of voiding behind the concrete block and concrete walls
  • Conduct close visual inspection to identify defects on plunge pool and spillway walls
  • Carry out voiding repairs on plunge pool East and West walls – concrete spray application (shotcrete works)
  • Carry out defect repair works (concrete and masonry) on plunge pool East and West walls
  • Carry out defect repair works on spillway

THE STORY WAY

Our project team worked in close collaboration with the Scottish Environment Protection Agency and Galloway Fisheries Trust during the plunge pool draining and concrete spray application works.

Consent restrictions were agreed allowing the project to complete successfully within the permitted time window. This ensured the works had no adverse effect on the fishes and the entire environment.

Story Contracting’s project team worked diligently and safely on site at Tongland Hydro Power Station. The work carried out is good quality, to budget, and within the timescales set.

Paul Tannock, Civil Engineer Drax

Related projects

View all
RWE Wind Farm
Energy

RWE Wind Farm

RWE Renewables

Energy
View project

Works were carried out to demolish an existing storage building, and replace it with a larger, modern structure.

View project
Bhlaraidh Wind Farm
Energy

Bhlaraidh Wind Farm

SSE Renewables

Energy
View project

SSE Renewables received planning consent to install an additional 15 turbines, which would generate up to 84MW.

View project
Cathkin BESS
Energy

Cathkin BESS

Ethical Power Connections

Energy
View project

The site was a greenfield location where a new 33kV metering substation was installed to facilitate this connection.

View project

To find out how we can help deliver your future project then get in touch