Cathkin BESS
Ethical Power Connections
The site was a greenfield location where a new 33kV metering substation was installed to facilitate this connection.
14
controlled blasts undertaken
75,000m3
site won material processed and placed
Due to the location of the project, there were several environmental restrictions that needed to be adhered to and a fulltime ECoW presence on site was necessary. The project team worked closely with our own inhouse environmental team as well as subcontractors to ensure that all works were undertaken safely and within environmental consents.
Ethical Power Connections
The site was a greenfield location where a new 33kV metering substation was installed to facilitate this connection.
"*" indicates required fields