Queen Street Tunnel Track Slab

Story Contracting were tasked with the delivery of the track slab system which was part of the renewal of Queen Street Tunnel’s degraded 40-year-old slab track working for Morgan Sindall. The project, part of a larger scheme at Queen Street is part of the ongoing Edinburgh Glasgow Improvement Programme (EGIP).

10,000t
of concrete &
rock removed

2,500m3
of concrete placed

Scope of Works

  • Demolition of 10,000 tonnes of existing concrete and rock
  • Construction of a concrete slab using 2500m3 of concrete
  • Installation of over 3km of drainage

The STORY Way

Access restrictions due to engineering trains and other external factors resulted in the programme slipping during its first phase.

A nine day recovery programme was produced and a combined team of Rail Scotland, Rail England, Story Construction and Story Plant who put in a tremendous effort pouring 90 metres of structural concrete each and every day to finish the first phase on time.

This momentum was maintained for the second phase and the structural concrete was completed five days early.

Delivering a Successful Solution

The project was able to celebrate success and demonstrate best practice within many areas. We held weekly coordination meetings with the client and other contractors working within the blockade. These were attended before a formal award was given, in order to maximise time in the planning phase and to gain the most benefit from the coordination plans.

Unforeseen delays were also carefully managed in a proactive manner, enabling the original completion date to be met. Ultimately this project demonstrated the collaborative working of a combined team formed by all parts of the Story Contracting business.

A fantastic effort by you and your team at Story Contracting to complete the concrete works ahead of programme. Well done and thanks to all involved.

Robert Ogg Morgan Sindall

Related projects

View all
Seaton South Embankment Upgrade
Rail

Seaton South Embankment Upgrade

Network Rail

Rail
View project

The project involved regrading approximately 280 metres of the embankment to enhance structural stability and improve rail safety.

View project
SPT Broomloan Depot
Rail

SPT Broomloan Depot

SPT

Rail
View project

Story Contracting Ltd were engaged by Ansaldo STS (Hitachi) as their principal contractor to support the comprehensive upgrade of the Glasgow Subway network for SPT (Strathclyde Partnership for Transport).

View project
Shields Road
Rail

Shields Road

Network Rail

Rail
View project

Story Contracting replaced a key bridge linking Pollokshields and Kinning Park, maintaining pedestrian access via a temporary footbridge while managing complex utility diversions, major excavations, and two disruptive possessions.

View project

To find out how we can help deliver your future project then get in touch