Penrith Station AFA

Construction of a new single span footbridge and associated lifts to provide improved access to the platforms for passengers with mobility issues using the station.

500 tonne crane installed
footbridge, lift shaft & stairs

Installation of lift pit & foundations
2 OROR possessions

Scope of Engineering Works

The scope of the project was to implement the following works:

  • Upgrades to the existing low voltage power supply
  • Installation of 3.5m deep mass fill foundations and lift pit over 2 OROR possessions
  • Installation of a footbridge, lift shafts and stairs, using a 500t crane to complete 14 lifts during one OROR possession
  • Installation of new ducting and M&E equipment to provide power, lighting and CCTV for the new lifts/structure and along the platforms
  • Finishing works to the platform and car park area including; drainage, re-surfacing, road markings, fencing and signage

The STORY Way

The piling, excavation and pouring of the foundations was completed during a series of OROR and ROR (Rules of the Route) possessions. The project team had prepared the foundations by installing formwork and tying the reinforcement.

The new structure was installed using a 500 tonne crane, then the lifts were installed. Finishing works to the site included the installation of lighting and CCTV, drainage upgrades, the re-surfacing of the car park and platforms and the testing of all mechanical, electrical and telecoms equipment.

Delivering a Successful Solution

Part of this projects success was due to the fact the key subcontractors such as the steel fabricator and lift contractor, were involved in the detailed design stage to ensure that they could advise on the buildability of the final solution. Before Story Contracting started work, meetings were held with other contractors carrying out major works in the area so we could all make the best use of the track access.

The team also collaborated with the station staff and programmed the work outside of station opening hours which meant minimum disruption to Virgin Trains and their customers.

The scheme has been excellently managed by Story. The standard of finish by the operatives, particularly the lift shafts, is of a high standard and behaviours demonstrated whilst working in and amongst passengers has been excellent. I’ve worked on a number of AFA projects now and Penrith is easily the best I’ve been involved with, a sentiment echoed by the wider team and by the Buildings RAM team.

Chris Atkins Network Rail

Related projects

View all
Seaton South Embankment Upgrade
Rail

Seaton South Embankment Upgrade

Network Rail

Rail
View project

The project involved regrading approximately 280 metres of the embankment to enhance structural stability and improve rail safety.

View project
SPT Broomloan Depot
Rail

SPT Broomloan Depot

SPT

Rail
View project

Story Contracting Ltd were engaged by Ansaldo STS (Hitachi) as their principal contractor to support the comprehensive upgrade of the Glasgow Subway network for SPT (Strathclyde Partnership for Transport).

View project
Shields Road
Rail

Shields Road

Network Rail

Rail
View project

Story Contracting replaced a key bridge linking Pollokshields and Kinning Park, maintaining pedestrian access via a temporary footbridge while managing complex utility diversions, major excavations, and two disruptive possessions.

View project

To find out how we can help deliver your future project then get in touch