Mersey Loop Track Slab Renewals

During a 5 month period, works were undertaken to renew the track slab within the Mersey Loop at Liverpool.

170m3 
concrete pump

1.2km
track slab renewed

90,000
man hours

The Scope

The key renewal works on the Mersey Loop involved:

• 170m3 of concrete pumped into positi on
• More than 1.2 Km of track slab renewed to date
• The installati on of 2,400m new running
• Over 90,000 man hours completed to date
• More than 3,600 new VIPA baseplates installed requiring 14,500 bolts to be cored and installed
• Eight spoil trains used to remove around 1,600 tonnes of breakout material
• Four rail drops delivering 2,400 metres of new rails
• 24/7 working

Delivering Succcess

One major success story from the project was the collaboration between our project team and a number of stakeholders involved with the project. Merseyrail, which operates the services on the Wirral Line, was a key stakeholder for this project.

The Story Way

We were able to reconfigure our programme to enable the reopening of James Street Platform 1 in February instead of June. The reopening allowed Merseyrail to run an increased service in addition to being Disability Discrimination Act compliant.

We were involved at an early stage which allowed lessons learned from previous schemes to be incorporated into both the designs and the works’ methodology. This in turn had a positive effect on health, safety and quality, as well as ensuring the project was delivered on programme and on budget.

We were able to reuse the existing concrete slab, saving both time and money for the client. We also involved specialist contractors who had worked on previous phases of track slab renewal. This ensured the knowledge and equipment was available to undertake the work safely and to a high standard. The scheme also utilised engineering trains to remove spoil from the site, reducing road traffic and ensuring the waste was recycled.

A big thank you to those who have worked unseen, under the city 24/7 to deliver the improvements that will benefit the city region in the long term. The collaborative approach between Story Contracting, Network Rail, MerseyTravel and all the other agencies who have helped deliver a successful project and kept the city of Liverpool moving.

Peter Glass Head of Performance Planning, Mersey Rail

Related projects

View all
Seaton South Embankment Upgrade
Rail

Seaton South Embankment Upgrade

Network Rail

Rail
View project

The project involved regrading approximately 280 metres of the embankment to enhance structural stability and improve rail safety.

View project
SPT Broomloan Depot
Rail

SPT Broomloan Depot

SPT

Rail
View project

Story Contracting Ltd were engaged by Ansaldo STS (Hitachi) as their principal contractor to support the comprehensive upgrade of the Glasgow Subway network for SPT (Strathclyde Partnership for Transport).

View project
Shields Road
Rail

Shields Road

Network Rail

Rail
View project

Story Contracting replaced a key bridge linking Pollokshields and Kinning Park, maintaining pedestrian access via a temporary footbridge while managing complex utility diversions, major excavations, and two disruptive possessions.

View project

To find out how we can help deliver your future project then get in touch