LEC1/45 Harrow Footbridge

Replacement of the existing 2 span wrought iron footbridge with a new single span aluminium footbridge in London.

The Project

The existing footbridge was a two-span wrought iron footbridge with brick abutments, brick wingwalls and a concrete deck in an overall poor to failed condition.

The latest detailed examination identified significant areas of breakdown of protective coating, resulting in corrosion to metallic elements throughout including loss of section to the main girders. There were also numerous brickwork defects to abutments and piers including fractured and spalled brickwork.

This was a challenging project due to the structure spanning both the West Coast Main Line and London Overground lines, and the only access being down a footpath within a residential area.

3no. 54-hour
possession

33m single span footbridge
 installed in single lift

Scope of Engineering Works

The aim of the project was to replace the existing two span wrought iron footbridge with a new single span aluminium footbridge. Works included:

  • Breakdown of existing wingwalls and reducing abutments
  • Removal of existing bridge deck, parapet and ancillaries
  • Construction of new substructure for the abutment extensions using bored piles
  • Construction of new cast in-situ concrete abutment extensions to both abutments
  • Installation of new PCC cill units onto new abutment extensions
  • Installation of new aluminium superstructure manufactured by Glück GmbH
  • Follow up works (rebuild brick parapets, complete structural drainage, install new access steps and reinstatement of approaches)

The STORY way

The project was originally planned to be undertaken by another contractor who had delivered the design, however had failed to deliver the project on multiple occasions. Story Contracting were then contacted in March 2018 to tender for the project. The project team developed a new methodology, for example the use of Kirow Rail Cranes over mobile cranes, to deliver a project which could not be delivered by other contractors.

The contract was awarded in May 2018, starting on site in July thus dictating a quick turnaround. Story Contracting met the challenge of a short planning phase by engaging with suppliers and third parties quickly and effectively, utilising previous experience and local contacts.

Delivering a Successful Solution

The project was able to celebrate success and demonstrated best practice within the following areas:

  • Delivered a high-profile project where other contractors had previously been unsuccessful
  • The involvement of experienced specialist contractors ensured that the knowledge and equipment was available to undertake the work safely and to a high standard
  • Early and effective consultation with Harrow Council ensured a good working relationship
  • Management of unforeseen change was proactive, resulting in additional works not affecting original completion date

Related projects

View all
Seaton South Embankment Upgrade
Rail

Seaton South Embankment Upgrade

Network Rail

Rail
View project

The project involved regrading approximately 280 metres of the embankment to enhance structural stability and improve rail safety.

View project
SPT Broomloan Depot
Rail

SPT Broomloan Depot

SPT

Rail
View project

Story Contracting Ltd were engaged by Ansaldo STS (Hitachi) as their principal contractor to support the comprehensive upgrade of the Glasgow Subway network for SPT (Strathclyde Partnership for Transport).

View project
Shields Road
Rail

Shields Road

Network Rail

Rail
View project

Story Contracting replaced a key bridge linking Pollokshields and Kinning Park, maintaining pedestrian access via a temporary footbridge while managing complex utility diversions, major excavations, and two disruptive possessions.

View project

To find out how we can help deliver your future project then get in touch