Holgate Depot

Story Contracting delivered new inspection pits inside Holgate Depot, as part of a series of enhancement to the Network Rail facility in order to expand operations.

3
pits installed

925m3
concrete poured

The Scope

The works involved:

• Stepped access/egress points installed at both end of the pits.
• Additional points installed in the centre of the pits to allow access/egress to both sides.
• Pits uniformly illuminated throughout the entire length, including suitable shield protection.
• Emergency pit lighting integrated within the maintenance bays lighting.
• The pits have been designed and installed to withstand a jacking capacity 25t along the fall width of the pits perimeter.
• Power connections points 110v/16amp, positioned every 5m within pit on alternative sides.
• Drainage sump provision and catch pit to the base of the pit to mitigate/collect oily leakage and to prevent trips & falls should there be a spillage.
• Removable side access perimeter protection to the pit to mitigate trips and falls.

Delivering Success

• Early Contractor involvement allowed scheme buildability to be discussed in advance of implementation, providing opportunity for value engineering and off-site fabrication to allow shorter timescales for installation and less disruption to the operational Depot.
• Management of unforeseen change was proactive, resulting in additional works not affecting operational requirements of the Depot.
• Collab approach with Network Rail & other contractors (e.g. Rothwell’s – electricity – and Network Rail Works Delivery team – track installation).

The Story Way

Story worked closely with the Network Rail project team, operation depot staff, the nearby Works Delivery team and wider Supply Chain – achieving success together through collaboration and open communication. Efficiencies were made through pits prefabrication off site, reducing Story’s time on site ensuring less disruption to the operational Depot.

Related projects

View all
Seaton South Embankment Upgrade
Rail

Seaton South Embankment Upgrade

Network Rail

Rail
View project

The project involved regrading approximately 280 metres of the embankment to enhance structural stability and improve rail safety.

View project
SPT Broomloan Depot
Rail

SPT Broomloan Depot

SPT

Rail
View project

Story Contracting Ltd were engaged by Ansaldo STS (Hitachi) as their principal contractor to support the comprehensive upgrade of the Glasgow Subway network for SPT (Strathclyde Partnership for Transport).

View project
Shields Road
Rail

Shields Road

Network Rail

Rail
View project

Story Contracting replaced a key bridge linking Pollokshields and Kinning Park, maintaining pedestrian access via a temporary footbridge while managing complex utility diversions, major excavations, and two disruptive possessions.

View project

To find out how we can help deliver your future project then get in touch