Seaton South Embankment Upgrade
Network Rail
The project involved regrading approximately 280 metres of the embankment to enhance structural stability and improve rail safety.
158m
pre-cast concrete z units
installed
329m
track slewed on the UP line
The project involved the following main phases:
• Demolition and reinstatement of platform 3 to modern standards.
• Installation of lift shafts, footbridge and stairs to platforms 2 & 3 to provide access for all.
• Installation of canopy to the full length of platform 3.
• Track slew to the UP line to allow adequate clearance between the UP & Down lines to accommodate the reintroduction of platform 3 for passenger services.
• Installation of compliant lighting, CCTV, PA & fire systems throughout the whole station.
• Relocation of signalling and telecoms equipment.
• Demolition of existing platform 3 wall.
The project was able to celebrate success and demonstrated best practice within the following areas:
• Early consultation with Hartlepool Council and affected local landowners resulted in good community relations.
• Early Contractor involvement allowed scheme buildability to be discussed in advance of implementation, providing opportunity for value engineering, including the slewing of the UP line efficiently and on time, as well as the works within the other blockades throughout the project.
•Regular site meetings with stakeholders and sub-contractors allowed for smooth construction phases, with any issues resolved within a timely manner.
Our project team worked in close collaboration with Network Rail, various stakeholders and the local council. Through this constant communication it allowed for efficient planning, reducing delays with regards to construction activities. This also allowed flexible track access ensuring a large proportion of the works could be completed on days, meaning close collaboration could take place between the whole project team.
Network Rail
The project involved regrading approximately 280 metres of the embankment to enhance structural stability and improve rail safety.