Eden Brows Repair Works

Repair works were undertaken on the Carlisle to Settle railway following a 500,000 tonne landslip in February 2016, closing the line near Armathwaite.

1,200m3
concrete poured
into the slab & wall

266
high strength piles
driven into bedrock

The Scope

The repair works of this historic railway included:

• One mile of access roads
• 16,000 tonnes of spoil removed from the site
• The installation of 226 piles – around 4,040 metres
• A 75-metre-long, one-metre-thick reinforced concrete slab
• A retaining wall which was 95 metres long and 4 metres high
• 1,200m³ of concrete poured in the slab and wall
• 6,000 tonnes of backfill
• 490 metres of track reinstalled
• 2,400 metres of track re-aligned
• 3,000 tonnes of new ballast installed
• 226 piles installed

The Story Way

After careful consideration during the design stage of the project, a piling solution was chosen. Two rows of highstrength steel piles were filled with concrete and driven into the sloping bedrock, forming a corridor upon which a one metre-thick slab and retaining wall could be constructed to support the track.

This landslip had a big impact on the local community. We used engineering trains to remove the spoil from site, import stone and pile casings so that we removed HGV movements from the local roads where possible. During the main works, we implemented 24-hour working to ensure the railway could be handed back on time and on budget, ahead of a planned re-opening celebration with the Flying Scotsman passing over the site.

Eden Brows has been a hugely challenging job, as I saw for myself last year. I am impressed and grateful to the innovative team that led this work and to Story and the other contractors who helped make it happen. Well done to you all. A great railway team effort.

Mark Carne CEO, Network Rail

Related projects

View all
Seaton South Embankment Upgrade
Rail

Seaton South Embankment Upgrade

Network Rail

Rail
View project

The project involved regrading approximately 280 metres of the embankment to enhance structural stability and improve rail safety.

View project
SPT Broomloan Depot
Rail

SPT Broomloan Depot

SPT

Rail
View project

Story Contracting Ltd were engaged by Ansaldo STS (Hitachi) as their principal contractor to support the comprehensive upgrade of the Glasgow Subway network for SPT (Strathclyde Partnership for Transport).

View project
Shields Road
Rail

Shields Road

Network Rail

Rail
View project

Story Contracting replaced a key bridge linking Pollokshields and Kinning Park, maintaining pedestrian access via a temporary footbridge while managing complex utility diversions, major excavations, and two disruptive possessions.

View project

To find out how we can help deliver your future project then get in touch