Burton Underpass
Ayrshire Roads Alliance
Essential works took place to replace the unsafe road crossing over Dunure Road by reopening a former railway tunnel as a new underpass.
1,462
Starter Bars installed to the foundations
75,000
Bricks & blocks used to construct flood defence walls
The Scope of the project was to design and implement the following works to both stores:
The flood walls to each elevation were constructed through a process of installing the brickwork in 1m lifts, along with 6mm steel bar reinforcement. After being left to cure, the team then mass filled the wall with concrete, repeating this step 3 times to each elevation in order to safely achieve the full 3m flood wall height.
The project was able to celebrate success and demonstrated best practice within the following areas:
Our project team were able to use our established relationship with Cluttons to work in close collaboration with their team. This ensured that any challenges were resolved quickly and efficiently so that the project was successfully completed within the agreed programme.
Ayrshire Roads Alliance
Essential works took place to replace the unsafe road crossing over Dunure Road by reopening a former railway tunnel as a new underpass.
"*" indicates required fields