Carlisle Station

Network Rail required platforms 1-3 to be renewed due to the current platforms not being compliant to the Network Rail standards.

Over 5,500
over-sail blocks placed

5,100m2
tarmac surfacing completed

The Scope

The project involved the following main phases:

• Provide a compliant platform’s to allow safe access and egress on / off passenger trains.
• Creation of platform drainage solution to existing outfall.
• Complete new over-sail, coper, tactile and surfacing to all platform on 1-3.
• Possession driven OLE alterations to raise the overheads in on Platform 1 and 3.
• Track lifts, wet bed renewal and ballast drops throughout Platform 1-3.
• Installation of ducting within the platform to futureproof the station for any future upgrades and OLE improvements preventing un-necessary future excavation of the platforms.
• Access methodology developed to accommodate 26T weight limit on the access bridge on only access route to compound – limited options for removing

Delivering Success

The project was able to celebrate success and demonstrated best practice within the following areas: Regular communication and engagement with the local heritage officer resulted in all final works being agreed and helped to build future relations for the next stages of works at the station.

Early Contractor involvement allowed scheme buildability to be discussed in advance of implementation, providing areas where works could be accurately sequenced and implemented without conflict with other work groups. Management of unforeseen change was proactive and progressed / turned around in quick manner due to the time constraints Story Contracting were held to with durations of platform closures.

The Story Way

Our project team worked in close collaboration with Avanti West Coast, the heritage officer and Network Rail throughout the project due to an ever-changing programme and design changes due to encountered issues which presented themselves.

Heritage consent restrictions were agreed allowing the project to complete successfully to a high quality. Project team carried out community litter picks in and around the station location and made several flower planters which were placed along the completed platform 3 to provide a little extra colour to the station.

Related projects

View all
Seaton South Embankment Upgrade
Rail

Seaton South Embankment Upgrade

Network Rail

Rail
View project

The project involved regrading approximately 280 metres of the embankment to enhance structural stability and improve rail safety.

View project
SPT Broomloan Depot
Rail

SPT Broomloan Depot

SPT

Rail
View project

Story Contracting Ltd were engaged by Ansaldo STS (Hitachi) as their principal contractor to support the comprehensive upgrade of the Glasgow Subway network for SPT (Strathclyde Partnership for Transport).

View project
Shields Road
Rail

Shields Road

Network Rail

Rail
View project

Story Contracting replaced a key bridge linking Pollokshields and Kinning Park, maintaining pedestrian access via a temporary footbridge while managing complex utility diversions, major excavations, and two disruptive possessions.

View project

To find out how we can help deliver your future project then get in touch