Seaton South Embankment Upgrade
Network Rail
The project involved regrading approximately 280 metres of the embankment to enhance structural stability and improve rail safety.
54
hour possession to replace the underbridge
100
metres of track renewed
Bridge lifted
5.2 metres
The scope of the project was to design and implement the following works:
• Construction of the new structure within the site compound
• Successfully replacing UB285/022 utilising a SPMT over a 54hr blockade
• Temporary works designed to allow access to carry works out safely
• Methodologies developed to enable works to take place in close proximity to the railway utilising
The project was able to celebrate success and demonstrated best practice within the following areas:
• Early consultation with the local council and close residents resulted in good community relations.
• Weekly meetings with the client resulted in good communication and understanding of the works.
• Proactively managing unforeseen delays enabling us to maintain our original completion date.
• Working efficiently with all associates involved as a team throughout out the project.
Prior to any works commencing we issued communications to all the residents in the surrounding area, detailing the works which would be carried out. This helped reduce the impact of our presence as the locals were aware of why we were there and how long for – an important factor as the road had to be closed permanently for a period of time and a diversion put in place.
Network Rail
The project involved regrading approximately 280 metres of the embankment to enhance structural stability and improve rail safety.