Arcow Quarry – Earthworks, Track & Footbridge

Arcow Quarry was a £2.5 million scheme to once again connect Tarmac’s quarry near Horton-in-Ribblesdale with national rail network. Story Contracting provided the design and implementation of the track and civils works.

The Project

Work commenced on site in July 2015. The project required a significant earthworks solution – the previous sidings formation was deemed unsuitable for modern requirements, particularly with regard to the curvature of the approach track. A new scheme was needed to connect Tarmac’s Quarry with the rail network, about 400 yards north of the old connection.

The solution consisted of the construction of a 640m new embankment, 300m of precurved track, 3 new sidings, installation of a refurbished footbridge and installation of new walkways.

Scope of Works

The scope of the project included the following works:

  • 120m of 1200mm diameter drainage was installed for the quarry operations
  • Creation of a new siding to allow loading activities
  • Installation of a footbridge over the siding to access the existing bridleway

 

  • New walkways and inspection routes were required throughout the length of the sidings
  • 500m of lineside track drainage was needed to work in conjunction with the track formation
  • Construction of 135m of ramp formed by new foundations

The STORY Way

Working closely with the designer allowed Story to liaise directly with Tarmac to design a solution that utilised the material quarried on site to construct the new embankment, backfill material to the loading ramp and cladding to the footbridge. This hugely assisted both the cost of the scheme but also the sheer logistics in avoiding importing thousands of tonnes of material.

There were some key constraints to overcome during the project but Story were able to resolve these issues by working with Bowland Ecology and the National Parks planning team. This allowed us to continue hitting milestones throughout the programme and deliver the project to a high standard.

A refurbished lattice footbridge was also installed onto stone-faced abutments and now provides an excellent vantage point from which to view the sidings.

Delivering a successful solution

The project progressed from planning stage to completion in little over a year, with the project timeline geared to a critical 78-hour line closure between 23rd – 27th October and vital preparatory works completed one week ahead of schedule.

GB Railfreight hauled the first trainload of road stone out of Arcow quarry in fifty years on 26th January 2016.

Story Contracting’s performance delivering this complex and comprehensive project has been exemplary. Despite demanding timescales and engineering challenges, a spectacular achievement has been realised in only 14 months due to their hard work and collaborative spirit.

Joelle Caldarelli Scheme Project Manager, Network Rail

Related projects

View all
Seaton South Embankment Upgrade
Rail

Seaton South Embankment Upgrade

Network Rail

Rail
View project

The project involved regrading approximately 280 metres of the embankment to enhance structural stability and improve rail safety.

View project
SPT Broomloan Depot
Rail

SPT Broomloan Depot

SPT

Rail
View project

Story Contracting Ltd were engaged by Ansaldo STS (Hitachi) as their principal contractor to support the comprehensive upgrade of the Glasgow Subway network for SPT (Strathclyde Partnership for Transport).

View project
Shields Road
Rail

Shields Road

Network Rail

Rail
View project

Story Contracting replaced a key bridge linking Pollokshields and Kinning Park, maintaining pedestrian access via a temporary footbridge while managing complex utility diversions, major excavations, and two disruptive possessions.

View project

To find out how we can help deliver your future project then get in touch