Story deliver £4m bridge replacement in Sutton Coldfield

18th May 2023

Uncategorised Rail

Story Contracting, on behalf of Network Rail, worked over the Easter weekend to help deliver a £4m bridge replacement in the heart of Sutton Coldfield.

The job involved a 100 hour blockade to remove and replace CBR2/32 Intersection Bridge, a railway bridge which allows freight to pass over the passenger lines behind Sutton Coldfield College.

Alex O’Donovan, Scheme Project Manager in Story’s Rail division said: “A tremendous effort from all involved to deliver this challenging scheme in the middle of Sutton Coldfield safely and on time to keep trains moving on this important freight route over the cross city line.”

Denise Wetton, Network Rail’s Central Route Director said : “Removing and replacing this railway bridge over just four days was a hugely ambitious task and I’d like to pay tribute to the dozens of engineers involved who worked around the clock to make sure trains could run as normal again.”

Read Network Rail’s press release here: Cross City line reopens to passengers after Easter railway bridge overhaul (networkrailmediacentre.co.uk)

 

Similar articles

View all
Securing the Future of the East Coast Main Line: £33m Browney Curve Stabilisation Project Completed Ahead of Schedule
25th April 2025

Securing the Future of the East Coast Main Line: £33m Browney Curve Stabilisation Project Completed Ahead of Schedule

Read more
Thornliebank Road bridge reopens ahead of schedule
25th April 2025

Thornliebank Road bridge reopens ahead of schedule

Read more
New wheel lathe operational at Allerton TrainCare Centre
20th February 2025

New wheel lathe operational at Allerton TrainCare Centre

Read more