Story Contracting Ltd were engaged by Ansaldo STS (Hitachi) as their principal contractor to support the comprehensive upgrade of the Glasgow Subway network for SPT (Strathclyde Partnership for Transport).
22,000t
of 6F5 used for regrade works
280m
regrade complete
The scope of the project was to design and implement the following works:
• Excavate and step the existing embankment face in 10m sections.
• Installation of Terram to the excavated sections.
• Installation of stone to the embankment face, decreasing the slope angle.
• Installation of safe cess walkway.
• Installation of drainage to the toe of the embankment.
• Install new access track, install new fence lines and reinstate the landowners land.
The project successfully demonstrated best practice across several key areas:
• Early engagement with the landowner, fostering positive community relations.
• Strategic sourcing from local quarries, securing better-than-expected rates for stone.
• Proactive management of unforeseen changes, ensuring timely completion despite additional works
The project team maintained close collaboration with both the designer and the landowner throughout the duration of the scheme. Ongoing and transparent
communication with the landowner ensured a clear and consistent dialogue, allowing any concerns or issues to be identified and resolved promptly. This proactive approach helped to mitigate potential delays.
SPT
Story Contracting Ltd were engaged by Ansaldo STS (Hitachi) as their principal contractor to support the comprehensive upgrade of the Glasgow Subway network for SPT (Strathclyde Partnership for Transport).