BAE Systems Enabling Works
BAE Systems
Story Contracting were contracted by BAE Systems to carry out the project which was a mixture of civils and building works to prepare the site for the new University of Cumbria facility.
20,000t
material utilised in cut and fill works
800m3
concrete poured to floors, pits and foundations
The project involved the following main elements of design and construction:
• Raising of ground levels as required to infill lower level existing topography and maintain existing factory floor level for the footprint of the proposed extension, incorporating steps in level for Curing gallery and closed duct etc.
• Construction of extension superstructure, including linking to existing structure and accommodating any future extensions
• Diversion of existing surface water drains to accommodate new gallery pits
• Excavation of gallery pits and service tunnel
• Construction of new gallery pits and floors
• Cladding works to roof and walls
• Design to accommodate services and machinery installation by Pirelli
• Internal fire resistant rapid roll doors and internal 2 hour fire resistant wall compartmentation upgrade
• Surface and roof drainage, including fire road land drains
• External ground levels raised for provision of perimeter fire road with stable embankment beyond
• Realignment of external site security fencing.
Due to machine delivery dates dictating the required programme completion date, this project was delivered within an challenging timeframe, which even Pirelli were sceptical could be achieved. 12 weeks into the project Pirelli made the decision to extend the building by an extra 2 bays (another 600m2). This was designed and constructed in less than 12 weeks to allow possession for the client to install further machinery procured by Pirelli Global.
Our long-standing relationship with the client enabled early engagement in a collaborative design process, resulting in time savings on the project. Further time savings were also generated through phased handovers, allowing Pirelli to proceed ahead of programme. Our commitment to being a stress-free contractor was also evident, with no disruption or downtime caused to Pirelli’s manufacturing process, despite works taking place in close proximity to the manufacturing line.
BAE Systems
Story Contracting were contracted by BAE Systems to carry out the project which was a mixture of civils and building works to prepare the site for the new University of Cumbria facility.
Defence Infrastructure Organisation (DIO)
Story Contracting were contracted by Landmarc to carry out the project to construct a new 1214m2 industrial style training building for the Defence Infrastructure Organisation (DIO) within the Catterick MOD base.
Holmen Iggesund
In 2021 Story were appointed to assist the design team to produce the most efficient construction sequence to carry out the construction of a new Effluent Treatment Plant at the Iggesund factory in Workington, Cumbria.
"*" indicates required fields