Through the project the Story team diligently liaised with stakeholders, effectively planned and delivered works to minimise any client disruption to ensure that client operations remained live in the occupied section of the building whilst the demolition works and gable erection / new cladding were installed. This included:
1. Design and erection of a temporary scaffold fire retardant structure to prevent weather ingress and protect occupants and materials in the occupied section of the structure.
2. Maintained safe through roads to allow the client to access / egress through the CDM site.
3. Continually liaised with stakeholders to phase works around sensitive client operations.