Innovation helps deliver platform extension

14th September 2018

News Rail

An innovative solution by Story Contracting helped deliver a project to extend two platforms at a railway station in a safer, more efficient way.

The £640,000 project on behalf of Network Rail also had a shorter site programme with less dependency on track access after Story used platform extensions pre-cast with stone cladding at Hebden Bridge just west of Halifax.

Story changed the design from traditional stonework to the pre-cast solution to extend Platform 2 by 56 metres as well as extending Platform 1 by 12 metres at the same time and at short notice.

The project was awarded to build the extension out of stone to match the existing platform but Story offered the alternative solution using the L-shaped pre-cast concrete units, pre-clad with 75mm to 100mm of thick stone on the front face to satisfy the planning requirements.

This alternative method was cost neutral but offered many benefits, which included:

  • Constructability input from the site team and supply chain engagement at design stage, with consideration to lifting and transportation, resulting in an optimised pre-cast unit shape
  • Maximised off-site fabrication in a safer, controlled environment
  • A shorter site programme duration and reduced track access requirements
  • The 23, 5.2-metre-long units were positioned in one week of section 5 mid-week possessions with just a four-hour working window per night
  • Reduced temporary works to retain ballast in the track support zone
  • Reduced manual handling for the large volume of stonework
  • Existing and future cable accommodation designed into the solution
  • Minimal maintenance required

Similar articles

View all
Securing the Future of the East Coast Main Line: £33m Browney Curve Stabilisation Project Completed Ahead of Schedule
25th April 2025

Securing the Future of the East Coast Main Line: £33m Browney Curve Stabilisation Project Completed Ahead of Schedule

Read more
Thornliebank Road bridge reopens ahead of schedule
25th April 2025

Thornliebank Road bridge reopens ahead of schedule

Read more
New wheel lathe operational at Allerton TrainCare Centre
20th February 2025

New wheel lathe operational at Allerton TrainCare Centre

Read more